Haldia Container
Terminal

Kolkata Port Trust awarded the Operation and Maintenance contract for Haldia Container Terminal to HICT for Integrated Container Handling operations for a period of 10 yrs. A highly motivated team handles operations efficiently, backed by knowledge, skill and computerised systems.

Equipment

Rail mounted quay crane
3
Rubber tyred gantry crane
4
Reach Stacker
3
Internal transfer vehicle
12

Facilities

  • Jetty - 7776 sq m
  • Quay Length - 432 m
  • Total Area - 95000 sq m
  • Green Belt - 800 sq m
  • Back reach - 4968 sq m
  • Total back-up area - 95,040 sq m
  • Container Stack Yard - 45500 sq m
  • Reefer Stark Yard - 24 plug points
  • Railway line - 1
  • Rail Siding - 650 m
  • Rail Yard - 1550 sq m
  • Hazardous cargo area - 160 sq m
  • Gate Complex - 4 lane
  • Administration Building - 223 sq m
  • Workshop - 1022 sq m
  • TGS - 1350

Contact Us

ADD Haldia International Container Terminal Pvt Ltd
Old P & T Building, Chiranjibpur Camp,
Dock Zone, Haldia 721 604,
West Bengal, India.
TEL +91 95474 11466
Registered
ADD
Godrej Coliseum, Office No. 801, 8th Floor, 'C' Wing, Behind Everard Nagar, Off. Somaiya Hospital Road, Sion East, Mumbai 400 022
CIN U61200MH2015PTC262125